Site and Safety Phase II– Installation of the outside retaining wall brick work is well underway. New lighting for the site is also being installed along the adjoining bridge walkway. On June 14 restoration of the stream north of the bridge will begin.
TUNE at HCC – Towson’s satellite campus, TUNE at HCC, is close to completion. The site work is complete, minor exterior and interior finishes are being installed and the furniture is expected to be delivered mid-June.
Burdick Hall phase III – The south wing renovations continue including upgrades to the locker rooms, corridors, lighting, plumbing, electrical, etc. This project is scheduled to be complete mid-summer.