Construction Update

Campus construction is continuing on schedule during the summer months. A description of the progression of each major project is below.

Campus Site and Safety Improvements
? The ramp extending from the Lecture Hall to Hawkins Hall and the Psychology Building will begin being removed during the first week of July.
? Access to the area of campus between Linthicum and the Psychology Building will be restricted during the removal.

College of Liberal Arts
? The new roadway between the Towsontown Parking Garage and the College of Liberal Arts building is now under construction.
? The masonry for the College of Liberal Arts is nearly done and expected to be completed in early July.
? Roofing is scheduled to begin in mid-July.
? Interior framing is complete at the 365′ level and in progress at the 380′ & 395′ level.
? Mechanical & electrical rough in is continuing at the 395′ and 410′ levels.

Central Utility Plant Addition
? The exterior CMU work is almost complete.
? The brick fa