TU home | T3 | Construction Update

Construction Update

Construction on the West Village Commons, West Village Garage, West Village Housing, and College of Liberal Arts projects continues to progress. Detailed updates and upcoming milestones for each project are listed below. For additional information on campus construction, go to {www.towson.edu/currentconstruction}. For information about how these projects may affect your vehicular and pedestrian traffic on campus, go to {www.towson.edu/constructionimpacts}, or view TU?s construction impacts map by going to {www.towson.edu/constructionmap}.

Campus Gateway
Completed winter 2012
? The gateway pillars on either side of the new entrance have been erected; brickwork on the pillars is now underway.
? Traffic signal masts are being erected above the gateway.
? Installation of the new University Avenue road will began this week.
? The area is being filled to bring the grade up to proposed elevations between Burdick Hall and CLA.

College of Liberal Arts ? Phase II
Opening August 2011
? Construction on phase II is complete!
? The paver sidewalk on the west side of CLA is complete.
? Furniture has been delivered to the building.
? Miscellaneous finishing work and touch-ups are being done.
? Utility work is ongoing in the area northeast of the Union.
? Landscaping and sidewalks are being installed around the Hawkins Hall/Psychology grand staircase.

Public Safety Building
Opening August 2012
? Building construction is slated to begin around the beginning of September.

West Village Commons
Opening August 2011
? Construction on the building is complete!
? all interior furniture has been delivered.
? Housing & Residence Life is now occupying the building; additional occupants will move in the coming months.
? Facilities training on the building is ongoing.

West Village Garage
Opening August 2011
? Erection of the precast components is complete.
? Masonry is near 100% complete.
? Interior build-out of mechanical, electrical and plumbing systems is ongoing.
? Landscaping and sidewalks are being installed; lighting will be added in the coming weeks.

West Village Housing Phase II ? Douglass and Barton Houses
Opening August 2011
? Final touch-up work is being completed.
? Landscaping and sidewalks are being installed.