Construction on Tiger Arena and Newell and Richmond renovations continues to progress. Detailed updates and upcoming milestones for each project are listed below. For additional information on campus construction, go to {www.towson.edu/currentconstruction}. For information about how these projects may affect your vehicular and pedestrian traffic on campus, go to {http://www.towson.edu/trafficimpacts}, or view TU?s construction impacts map by going to {www.towson.edu/constructionmap}. To view pedestrian access information, visit {http://www.towson.edu/adminfinance/facilities/construction/documents/2012SpringConstructionMap.pdf}.

Campus Site and Safety ?Landscaping will take place spring of 2012. Corrections to the east wall of the service road retaining wall are complete.

West Village Garage – Punch list and warranty items continue.
Newell Richmond Renovations ? Interior and exterior renovations continue to progress.

Ward and West ? Design is ongoing. Early utility work is scheduled for June 2012.

Tiger Arena ? Steel erection is about 70% complete. Precast concrete is about 90% complete. Foundations and concrete walls are nearly complete with remaining poured in place concrete about 50% complete. New gas service installation to take place in late March, 2012.

West Village Housing ? HVAC systems under remedial action by contractor.