TU home | T3 | Construction update: BGE Cross Campus and Towsontown Blvd.

Construction update: BGE Cross Campus and Towsontown Blvd.

Construction work is still ongoing on Cross Campus and Towsontown Boulevard. As a result, some traffic delays may be experienced along construction routes.

 BGE Cross Campus Project

Major phases of the BGE roadwork that began in the 2017 spring term have been completed. The installation of underground cables along Towsontown Boulevard and Osler Drive have been finished. Likewise, the BGE feeder project was completed earlier this month.

The removal of the old equipment for the East Sheppard Substation work is ongoing and is in its final stages. We do not expect this to affect traffic or student activities.

Towsontown Blvd.  Roadwork

The first phase of the county project to widen the Towsontown Blvd. and create additional turn lanes into Osler drive was finished in late December 2017. As result, the installation of sewer pipes which is the second phase of the project began earlier this week. We expect this phase to last through the spring term and be completed by summer 2018.

During this time, there will be lane reductions and changes to accommodate the work that is being done. Since this work began in the west of Osler Drive, we expect it to progress eastwards towards Burke Avenue.

Impacts

While we do not anticipate traffic delays on Cross Campus, we expect that there will be some major delays along the Osler/Towsontown intersection due to the sewer installation. We encourage road users to plan accordingly.

Information about this roadwork was previously posted in December 2016, February 2017, earlymid and late May 2017, early and late June 2017, August 2017 and December 2017.  

, , ,