West Village Housing Phase 3&4 – Opening fall term 2016
- Exterior (adding bricks) and interior (wall construction, plumbing and electric wires) progress continues
Burdick Hall Expansion Project – Opening late fall 2017
- Caisson drilling (drilling necessary for construction) and concrete foundation work continues. 90 of the 104 caissons have been drilled and filled with concrete.
Residence Tower Renovations – Construction to begin fall of 2016
- Design for this project is underway and is expected to be complete by May 2016.
Newell Dining Hall Renovations – Construction to begin early summer 2016
- Design is complete