West Village Housing Phase 3&4Opening fall term 2016

  • Exterior (adding bricks) and interior (wall construction, plumbing and electric wires) progress continues

Burdick Hall Expansion Project Opening late fall 2017

  • Caisson drilling (drilling necessary for construction) and concrete foundation work continues. 90 of the 104 caissons have been drilled and filled with concrete.

Residence Tower Renovations Construction to begin fall of 2016

  • Design for this project is underway and is expected to be complete by May 2016.

Newell Dining Hall Renovations – Construction to begin early summer 2016

  • Design is complete