Campus construction is continuing to progress on campus throughout the fall. Updates on campus construction projects are posted below. For more information on campus construction, go to {http://www.towson.edu/construction}.

College of Liberal Arts – Phase Two

? The steel frame of the glass gallery connecting phase two and phase one of the building is 50% erected.
? The exterior masonry is in progress on the easternmost portion of the building.
? The brick is nearing completion on the middle portion of the building.
? Wall framing is in progress on all floors of the center building.
? Window system installation will begin in the coming weeks.

Newell Dining Recycling and Refuse Depot

? This project was completed at the end of October.

West Village Commons Construction Update

? Concrete foundations are being installed along the hillside south of Emerson Drive.
? The first level concrete foundations which rest on stone are being installed.
? The first level concrete foundations which rest on dirt are being supported by a crushed stone pier called a Geopier, which is being installed.
? The first level?s concrete elevator shaft, walls and columns are being installed.

Campus Site and Safety

? The grand stairs between Hawkins Hall and the Psychology Building continues to be developed and is on schedule for a March 2010 completion.
? The bridge between Hawkins Hall and the Psychology Building is almost complete and is now on schedule for an early December opening.
? Construction on the Lecture Hall Plaza is on schedule to begin this January.
? The remaining concrete ramp by the Lecture Hall will be removed during the winter 2010 minimester.

Thank you for your cooperation and patience? a new and greater campus is coming your way!